The ceremonial first ignition of burners for heating-up and drying new lining coke oven battery no. 11

On 12. 7. 2016 held the ceremonial lighting of the burners to start the drying and heating-up of the battery under the investment project “Modernization of coke oven battery no. 11”, Trinecke Zelezarny a.s. HUTNI PROJEKT Frydek-Mistek a.s. provides within this investment activity of Thermal control division for the construction and start-up activities associated with…

Production of coke – Repair walls of coke oven No. 7

Category: Coke Location: Ostrava – Přívoz, Coke plant Svoboda Tenderer: OKK Koksovny a.s. Realization: 2015-2017   Description: Company HUTNÍ PROJEKT Frýdek-Místek a.s. has carried out the services by the Thermo Technical department. Repaired part of the coke-oven refractories has been cooled, thermal regime was kept during disassemly and brickworks, followed by regulation of repaired part.

Industrial buildings: De-dusting system of charging blast furnace 2 and 4

Category: Industrial Buildings Location: Ostrava Customer: ArcelorMittal Ostrava, Inc. Type of construction: New Realization: 2015 Description: The project´s aim was reduction of fugitive emissions from the Blast furnace charging system 2 and 4 – That was done by replacing of the existing electrostatic precipitators for fabric filters and the entire replacement and revamping of the…

Industrial facilities – Decreasing of fugitive emissions

Category: Industrial Buildings Location: Ostrava Customer: ArcelorMittal Ostrava, Inc. Type of construction: New Installation Realization: 2014-2015 Description: During the erection was the existing de-dusting system dismounted. They were built two new filtration plant including new chimneys, switching station, compressor station. There was installed new de-dusting duct for all the technological equipment and the cooling belts.…